Improvements to Kings Highway (CR-551S) from Market Street (CR-634) to Hopkins Road (CR-647)

Kings Highway Traffic Control notice

Segment 1

Work on crosswalks, curbs and sidewalks continues for the week

Reconstruction of intersection at Market with detours may start mid-week and run into the week of May 5th.

Segment 2

Daytime work during the early week to inspect sewer lines – no traffic impact

Segment 3

Sanitary sewer work continues – detours used during the day as usual to allow crews to safely excavate material from the work area and install new pipe.

Work on sidewalks and driveways will resume the week of May 5th.

Project Information

Name of Project:  Improvements to Kings Highway (CR-551S) from Market Street (CR-634, MP 1.23) to Hopkins Road (CR-647, MP 3.65) Boroughs of Mount Ephraim, Audubon, and Haddon Heights, Camden County, NJ

Start Date: Tentatively, Monday, September 16, 2024

Contract Time: Substantial completion = 340 calendar days

Final completion = 380 calendar days

Limits: Kings Highway (CR-551S) from Market Street (CR-634, MP 1.23) to Hopkins Road (CR-647, MP 3.65) Boroughs of Mount Ephraim, Audubon, and Haddon Heights, Camden County, NJ

A summary of the accelerated schedule is below:

  • 11/18-11/21: 10-hour shifts, 7 am – 5 pm
  • 11/22: Standard 8-hour shift, 7 am – 3 pm
  • Saturday 11/23: Extra 8-hour shift, 7 am – 3 pm
  • 11/25-11/27: 10-hour shifts, 7 am – 5 pm
  • 11/28-11/29: No work
  • 12/2-12/6: 10-hour shifts, 7 am – 5 pm
  • 12/9-12/13: Tentative Standard 8-hour shift, 7 am – 3 pm (based on previous progress)
  • 12/16-12/20: Tentative Standard 8-hour shift, 7 am – 3 pm (based on previous progress)
  • 12/23: Modify traffic control based upon extent of paving in Segment 3
  • 12/24-/4: Holiday shut down

Project Highlights:

  •  Milling and/or removal of existing concrete pavement and installation of hot-mix asphalt pavement
  • Resurfacing from Market Street (CR-634) to Hillside Avenue (CR-661)
  • Full-depth reconstruction from Hillside Avenue (CR-661) to West Atlantic Avenue (CR-727)
  •  Resurfacing from West Atlantic Avenue (CR-727) to Hopkins Road
  •  Improvements and rehabilitation to existing storm sewer system
  •  Cleaning and lining of existing sanitary sewer system and lateral replacement
  •  Concrete vertical curb, sidewalk, and ADA-accessible curb ramps
  •  Traffic striping, signage, and raised pavement markers

Total Estimated Cost: $10,745,085.83

Contractor: South State, Inc.

Questions? Contact:
Paul Nolan, Project Manager, Colliers Engineering & Design, (732) 704-5931
James Winckowski, Camden County Engineer, (856) 382-2699
Kyle Ebersole, Assistant Camden County Engineer, (856) 566-2968

Project Segments

Market St. to Rt. 168

Progress15%

Rt. 168 to Hillside Ave.

Progress95%

Hillside Ave. to West Atlantic Ave.

STG 1 Progress80%
STG 2 Progress40%

West Atlantic Ave. to Hopkins Rd.

Progress15%

Bi-Weekly Progress Reports

Work Schedule

WeekActivityLocations
3/31-4/11Concrete removalSegment 3, Hillside Ave to West Atlantic Ave
3/31-4/11Sanitary sewer main, laterals, and cleanoutsSegment 3, Hillside Ave to West Atlantic Ave
3/31-4/3Curbs, sidewalks, & drivewaysSegment 4, West Atlantic Ave. to Hopkins Rd.
4/2-4/4Full depth reclamationSegment 3, Hillside Ave to West Atlantic Ave
4/4-4/11Curbs, sidewalks, and drivewaysSegment 1, Market St to Rt 168

Traffic Control

Please be advised that Kings Highway (CR-551S) at the intersection with Market Street (CR 634) will undergo curb, sidewalk and driveway improvements in Mount Ephraim starting on Monday, March 10, 2025 weather permitting. This work can be done with shoulder closures and lane shifts, and should not have an impact on normal two-way traffic. Working hours will be 7:00 AM to 5:00 PM.

If you have any questions or need any further information, please contact Kyle Ebersole, Camden County Assistant Engineer, 856-566-2968 or Paul Nolan, Colliers Engineering, 732-704-5931. We apologize for any inconvenience this work may cause and appreciate your patience and understanding.

Join Our Mailing List

Enter your email below to be notified of project news, events, and important updates.